Ružín II HPP

About power plant

Built up on the balancing reservoir downstream the Ružín pumped storage power plant (PSPP), the Ružín II small hydro power plant processes evenly flow rates from peak-load operation of the the PSPP. There is installed a single set featuring a direct-flow Kaplan turbine at the utility.
Zobraziť viac
MVE Ružín IIMVE Ružín IIMVE Ružín IIMVE Ružín IIMVE Ružín II
  • MVE Ružín II
  • MVE Ružín II
  • MVE Ružín II
  • MVE Ružín II
  • MVE Ružín II

Deeper insight

Technical parameters
Category
run-of-river
Installed capacity MW
1,8 MW
Stream
Hornád
Type of turbine
Kaplan - horizontal
Flow rate
1x16 m3.s-1
Number of turbo-sets
1
Commissioned in
1974
Aver. annual generation GWh
6 GWh