Rakovec HPP

About power plant

Commissioned in 1912, the Rakovec small HPP is the oldest of Slovenské elektrárne hydroelectric power plant. There are two sets featuring a Francis turbine installed at it and the entire basic technologic equipment is original.
Zobraziť viac

Deeper insight

Technical parameters
Category
reservoir
Installed capacity MW
0,5 MW
Stream
Hnilec
Type of turbine
Francis
Flow rate
n/a
Number of turbo-sets
2
Commissioned in
1912
Aver. annual generation
0,633 GWh