About power plant

Sučany hydroelectric power plant is located on the diversion channel downstream the Krpeľany HPP, therefore its maximum usable flow is the same as that at the higher-laying stage. This principle applies to all of the diversion hydroelectricpower plants. Thanks to a higher head, also the installed capacity of this plant is higher as compared to the Krpeľany HPP.
Zobraziť viac

Deeper insight

Technical parameters
Category
canal
Installed capacity
38,4 MW
Stream
Váh
Type of turbine
Kaplan
Flow rate
3x70 m3.s-1
Number of turbo-sets
3
Commissioned in
1958
Aver. annual generation
95,3 GWh